rfi-management — Claude Code skill: what it does, how to install

rfi-management tracks construction RFIs in an Excel register, monitors resolution deadlines, and logs impacts on project budget and timeline.

MIT 131 installs ★ 434 updated 2026-10-19

Install into Claude Code · Skills CLI (Vercel) All methods and platforms ↓
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill rfi-management -a claude-code
Open on GitHub

What rfi-management does

This skill structures construction Requests for Information into a defined workflow. It logs inquiries using a data schema that tracks CSI specification codes, drawing sheet references, and building locations. Each record captures the submitting contractor, assigned reviewer, priority status, financial implications, and schedule delays tied to change order numbers.

Under the hood, an RFIManager class stores and updates project inquiries inside an Excel spreadsheet named rfi_log_{project_id}.xlsx using pandas. When creating an entry without a specified deadline, the logic automatically sets a 7-day turnaround window. Without python3 available in your system path, the underlying automation scripts will not execute.

What it helps with

  • maintain a centralized Excel log for project RFIs
  • track seven-day response deadlines across design teams
  • calculate budget impacts and schedule delays per inquiry
  • link engineering questions directly to drawing sheets and CSI sections

Example prompts for the agent

  • Create a high-priority RFI for drawing A-101 on project PRJ-42
  • Inspect open RFIs in the PRJ-42 register and show overdue items
  • Close RFI-005, log the structural engineer response, and record a 3-day delay

How to install rfi-management

1Skills CLI (Vercel)

npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill rfi-management -a claude-code

2Manually: put the files in place

~/.claude/skills/rfi-management/SKILL.md

Copy the whole skill folder; for one project use .claude/skills/rfi-management/

Step by step, with commands for each platform: How to install skills in Claude Code: five ways

Questions about rfi-management

How do I install rfi-management in Claude Code?

Run npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill rfi-management -a claude-code in your terminal.

Where does the skill keep inquiry records?

The code maintains an Excel spreadsheet named rfi_log_{project_id}.xlsx using the pandas library.

What turnaround time does it set by default?

If you do not specify a deadline, the system automatically sets date_required to 7 days after the submission date.

Source text

SKILL.md · MIT
---
name: "rfi-management"
description: "Complete RFI (Request for Information) management system. Create, track, route, and analyze RFIs with automatic notifications and response deadline tracking."
homepage: "https://datadrivenconstruction.io"
metadata: {"openclaw": {"emoji": "📋", "os": ["darwin", "linux", "win32"], "homepage": "https://datadrivenconstruction.io", "requires": {"bins": ["python3"]}}}
---
# RFI Management System for Construction

Comprehensive system for managing Requests for Information (RFIs) throughout the construction project lifecycle.

## Business Case

**Problem**: RFI management is chaotic:
- RFIs get lost in email threads
- Response deadlines missed
- No visibility into RFI status
- Difficult to track cost/schedule impacts
- Manual logging wastes hours weekly

**Solution**: Structured RFI management that:
- Auto-assigns RFI numbers
- Routes to correct parties
- Tracks response deadlines
- Sends automatic reminders
- Maintains audit trail
- Analyzes trends and impacts

**ROI**: 60% faster RFI response time, 90% reduction in lost RFIs

## RFI Workflow

```
┌──────────────────────────────────────────────────────────────────────┐
│                        RFI LIFECYCLE                                  │
├──────────────────────────────────────────────────────────────────────┤
│                                                                       │
│   ┌─────────┐    ┌─────────┐    ┌─────────┐    ┌─────────┐          │
│   │ CREATE  │───►│ SUBMIT  │───►│ REVIEW  │───►│ RESPOND │          │
│   │         │    │         │    │         │    │         │          │
│   │ • Draft │    │ • Route │    │ • Assign│    │ • Answer│          │
│   │ • Attach│    │ • Notify│    │ • Track │    │ • Approve│         │
│   └─────────┘    └─────────┘    └─────────┘    └─────────┘          │
│        │              │              │              │                │
│        ▼              ▼              ▼              ▼                │
│   ┌─────────────────────────────────────────────────────────────┐   │
│   │                    RFI DATABASE                              │   │
│   │  • RFI Log        • Attachments      • Response History     │   │
│   │  • Status Track   • Cost Impacts     • Schedule Impacts     │   │
│   └─────────────────────────────────────────────────────────────┘   │
│                                                                       │
│   ┌─────────┐    ┌─────────┐    ┌─────────┐                         │
│   │ CLOSE   │◄───│ VERIFY  │◄───│IMPLEMENT│                         │
│   │         │    │         │    │         │                         │
│   │ • Archive│   │ • Check │    │ • Action│                         │
│   │ • Report│    │ • Accept│    │ • Update│                         │
│   └─────────┘    └─────────┘    └─────────┘                         │
│                                                                       │
└──────────────────────────────────────────────────────────────────────┘
```

## Data Structure

### RFI Log Schema

```python
RFI_SCHEMA = {
    # Identification
    'rfi_number': str,          # RFI-001, RFI-002, etc.
    'project_id': str,          # Project identifier
    'revision': int,            # Revision number (0, 1, 2...)

    # Description
    'subject': str,             # Brief title
    'question': str,            # Detailed question
    'spec_section': str,        # CSI spec reference
    'drawing_ref': str,         # Drawing reference (A-101, S-201)
    'location': str,            # Building/floor/area

    # Parties
    'submitted_by': str,        # Originator name
    'submitted_by_company': str,# Originator company
    'assigned_to': str,         # Responsible party
    'cc_list': list,            # Additional recipients

    # Dates
    'date_submitted': date,     # When submitted
    'date_required': date,      # When response needed
    'date_responded': date,     # When answered
    'date_closed': date,        # When closed

    # Status
    'status': str,              # Draft/Open/Pending/Answered/Closed
    'priority': str,            # Critical/High/Medium/Low

    # Response
    'response': str,            # Answer text
    'response_by': str,         # Who answered
    'attachments': list,        # File links

    # Impact
    'cost_impact': bool,        # Has cost impact?
    'cost_amount': float,       # Estimated cost
    'schedule_impact': bool,    # Has schedule impact?
    'schedule_days': int,       # Days of delay
    'change_order_ref': str,    # Related CO number
}
```

## Python Implementation

```python
import pandas as pd
from datetime import datetime, date, timedelta
from typing import Optional, List, Dict
from dataclasses import dataclass, field
from enum import Enum
import uuid

class RFIStatus(Enum):
    DRAFT = "Draft"
    OPEN = "Open"
    PENDING = "Pending Review"
    ANSWERED = "Answered"
    CLOSED = "Closed"
    VOID = "Void"

class RFIPriority(Enum):
    CRITICAL = "Critical"  # Stops work
    HIGH = "High"          # Impacts critical path
    MEDIUM = "Medium"      # Standard
    LOW = "Low"            # Informational

@dataclass
class RFI:
    """Request for Information data class"""
    rfi_number: str
    project_id: str
    subject: str
    question: str

    # Optional fields with defaults
    spec_section: str = ""
    drawing_ref: str = ""
    location: str = ""
    submitted_by: str = ""
    submitted_by_company: str = ""
    assigned_to: str = ""
    cc_list: List[str] = field(default_factory=list)

    date_submitted: date = field(default_factory=date.today)
    date_required: date = None
    date_responded: date = None
    date_closed: date = None

    status: RFIStatus = RFIStatus.DRAFT
    priority: RFIPriority = RFIPriority.MEDIUM

    response: str = ""
    response_by: str = ""
    attachments: List[str] = field(default_factory=list)

    cost_impact: bool = False
    cost_amount: float = 0.0
    schedule_impact: bool = False
    schedule_days: int = 0
    change_order_ref: str = ""

    revision: int = 0

    def __post_init__(self):
        if self.date_required is None:
            # Default: 7 days for response
            self.date_required = self.date_submitted + timedelta(days=7)


class RFIManager:
    """Complete RFI management system"""

    def __init__(self, project_id: str, storage_path: str = None):
        self.project_id = project_id
        self.storage_path = storage_path or f"rfi_log_{project_id}.xlsx"
        self.rfis: Dict[str, RFI] = {}
        self._load_rfis()

    def _load_rfis(self):
        """Load RFIs from storage"""
        try:
            df = pd.read_excel(self.storage_path)
            for _, row in df.iterrows():
                rfi = RFI(
                    rfi_number=row['rfi_number'],
                    project_id=row['project_id'],
                    subject=row['subject'],
                    question=row['question'],
                    status=RFIStatus(row['status']),
                    priority=RFIPriority(row.get('priority', 'Medium'))
                )
                self.rfis[rfi.rfi_number] = rfi
        except FileNotFoundError:
            pass

    def _save_rfis(self):
        """Save RFIs to storage"""
        records = []
        for rfi in self.rfis.values():
            records.append({
                'rfi_number': rfi.rfi_number,
                'project_id': rfi.project_id,
                'subject': rfi.subject,
                'question': rfi.question,
                'spec_section': rfi.spec_section,
                'drawing_ref': rfi.drawing_ref,
                'location': rfi.location,
                'submitted_by': rfi.submitted_by,
                'submitted_by_company': rfi.submitted_by_company,
                'assigned_to': rfi.assigned_to,
                'date_submitted': rfi.date_submitted,
                'date_required': rfi.date_required,
                'date_responded': rfi.date_responded,
                'date_closed': rfi.date_closed,
                'status': rfi.status.value,
                'priority': rfi.priority.value,
                'response': rfi.response,
                'response_by': rfi.response_by,
                'cost_impact': rfi.cost_impact,
                'cost_amount': rfi.cost_amount,
                'schedule_impact': rfi.schedule_impact,
                'schedule_days': rfi.schedule_days,
                'change_order_ref': rfi.change_order_ref
            })

        df = pd.DataFrame(records)
        df.to_excel(self.storage_path, index=False)

    def _get_next_number(self) -> str:
        """Generate next RFI number"""
        existing = [int(r.rfi_number.split('-')[1])
                   for r in self.rfis.values()
                   if r.rfi_number.startswith('RFI-')]
        next_num = max(existing, default=0) + 1
        return f"RFI-{next_num:04d}"

    def create_rfi(
        self,
        subject: str,
        question: str,
        submitted_by: str,
        submitted_by_company: str,
        assigned_to: str,
        spec_section: str = "",
        drawing_ref: str = "",
        location: str = "",
        priority: RFIPriority = RFIPriority.MEDIUM,
        days_for_response: int = 7,
        attachments: List[str] = None
    ) -> RFI:
        """Create new RFI"""

        rfi_number = self._get_next_number()

        rfi = RFI(
            rfi_number=rfi_number,
            project_id=self.project_id,
            subject=subject,
            question=question,
            spec_section=spec_section,
            drawing_ref=drawing_ref,
            location=location,
            submitted_by=submitted_by,
            submitted_by_company=submitted_by_company,
            assigned_to=assigned_to,
            priority=priority,
            date_required=date.today() + timedelta(days=days_for_response),
            attachments=attachments or []
        )

        self.rfis[rfi_number] = rfi
        self._save_rfis()

        return rfi

    def submit_rfi(self, rfi_number: str) -> RFI:
        """Submit RFI for response"""
        rfi = self.rfis.get(rfi_number)
        if not rfi:
            raise ValueError(f"RFI {rfi_number} not found")

        if rfi.status != RFIStatus.DRAFT:
            raise ValueError(f"RFI {rfi_number} already submitted")

        rfi.status = RFIStatus.OPEN
        rfi.date_submitted = date.today()
        self._save_rfis()

        # Trigger notification
        self._notify_submission(rfi)

        return rfi

    def respond_to_rfi(
        self,
        rfi_number: str,
        response: str,
        response_by: str,
        attachments: List[str] = None,
        cost_impact: bool = False,
        cost_amount: float = 0.0,
        schedule_impact: bool = False,
        schedule_days: int = 0
    ) -> RFI:
        """Provide response to RFI"""
        rfi = self.rfis.get(rfi_number)
        if not rfi:
            raise ValueError(f"RFI {rfi_number} not found")

        rfi.response = response
        rfi.response_by = response_by
        rfi.date_responded = date.today()
        rfi.status = RFIStatus.ANSWERED

        if attachments:
            rfi.attachments.extend(attachments)

        rfi.cost_impact = cost_impact
        rfi.cost_amount = cost_amount
        rfi.schedule_impact = schedule_impact
        rfi.schedule_days = schedule_days

        self._save_rfis()

        # Trigger notification
        self._notify_response(rfi)

        return rfi

    def close_rfi(self, rfi_number: str, change_order_ref: str = None) -> RFI:
        """Close RFI after implementation"""
        rfi = self.rfis.get(rfi_number)
        if not rfi:
            raise ValueError(f"RFI {rfi_number} not found")

        rfi.status = RFIStatus.CLOSED
        rfi.date_closed = date.today()
        if change_order_ref:
            rfi.change_order_ref = change_order_ref

        self._save_rfis()
        return rfi

    def get_overdue_rfis(self) -> List[RFI]:
        """Get list of overdue RFIs"""
        today = date.today()
        return [
            rfi for rfi in self.rfis.values()
            if rfi.status == RFIStatus.OPEN
            and rfi.date_required < today
        ]

    def get_due_soon_rfis(self, days: int = 3) -> List[RFI]:
        """Get RFIs due within specified days"""
        today = date.today()
        cutoff = today + timedelta(days=days)
        return [
            rfi for rfi in self.rfis.values()
            if rfi.status == RFIStatus.OPEN
            and today <= rfi.date_required <= cutoff
        ]

    def get_rfis_by_status(self, status: RFIStatus) -> List[RFI]:
        """Get RFIs by status"""
        return [r for r in self.rfis.values() if r.status == status]

    def get_rfis_by_assignee(self, assignee: str) -> List[RFI]:
        """Get RFIs assigned to specific party"""
        return [r for r in self.rfis.values() if r.assigned_to == assignee]

    def get_statistics(self) -> dict:
        """Get RFI statistics"""
        all_rfis = list(self.rfis.values())

        if not all_rfis:
            return {'total': 0}

        open_rfis = [r for r in all_rfis if r.status == RFIStatus.OPEN]
        closed_rfis = [r for r in all_rfis if r.status == RFIStatus.CLOSED]

        # Calculate response times for closed RFIs
        response_times = []
        for rfi in closed_rfis:
            if rfi.date_responded and rfi.date_submitted:
                days = (rfi.date_responded - rfi.date_submitted).days
                response_times.append(days)

        # Cost and schedule impacts
        cost_rfis = [r for r in all_rfis if r.cost_impact]
        schedule_rfis = [r for r in all_rfis if r.schedule_impact]

        return {
            'total': len(all_rfis),
            'open': len(open_rfis),
            'closed': len(closed_rfis),
            'overdue': len(self.get_overdue_rfis()),
            'avg_response_days': sum(response_times) / len(response_times) if response_times else 0,
            'with_cost_impact': len(cost_rfis),
            'total_cost_impact': sum(r.cost_amount for r in cost_rfis),
            'with_schedule_impact': len(schedule_rfis),
            'total_schedule_days': sum(r.schedule_days for r in schedule_rfis),
            'by_priority': {
                p.value: len([r for r in all_rfis if r.priority == p])
                for p in RFIPriority
            },
            'by_assignee': self._group_by_assignee(all_rfis)
        }

    def _group_by_assignee(self, rfis: List[RFI]) -> dict:
        """Group RFIs by assignee"""
        result = {}
        for rfi in rfis:
            if rfi.assigned_to not in result:
                result[rfi.assigned_to] = {'total': 0, 'open': 0}
            result[rfi.assigned_to]['total'] += 1
            if rfi.status == RFIStatus.OPEN:
                result[rfi.assigned_to]['open'] += 1
        return result

    def _notify_submission(self, rfi: RFI):
        """Send notification for new RFI"""
        # Implement email/Telegram notification
        print(f"📋 New RFI submitted: {rfi.rfi_number} - {rfi.subject}")
        print(f"   Assigned to: {rfi.assigned_to}")
        print(f"   Due: {rfi.date_required}")

    def _notify_response(self, rfi: RFI):
        """Send notification for RFI response"""
        print(f"✅ RFI responded: {rfi.rfi_number} - {rfi.subject}")
        print(f"   Response by: {rfi.response_by}")

    def generate_report(self, output_path: str = None) -> str:
        """Generate RFI status report"""
        stats = self.get_statistics()

        report = f"""
RFI STATUS REPORT
Project: {self.project_id}
Generated: {datetime.now().strftime('%d.%m.%Y %H:%M')}

SUMMARY
═══════════════════════════════════════
Total RFIs:           {stats['total']}
Open:                 {stats['open']}
Closed:               {stats['closed']}
Overdue:              {stats['overdue']}
Avg Response Time:    {stats['avg_response_days']:.1f} days

IMPACT ANALYSIS
═══════════════════════════════════════
RFIs with Cost Impact:     {stats['with_cost_impact']}
Total Cost Impact:         ${stats['total_cost_impact']:,.2f}
RFIs with Schedule Impact: {stats['with_schedule_impact']}
Total Schedule Days:       {stats['total_schedule_days']}

BY PRIORITY
═══════════════════════════════════════
"""
        for priority, count in stats['by_priority'].items():
            report += f"{priority}: {count}\n"

        report += """
BY ASSIGNEE (Open)
═══════════════════════════════════════
"""
        for assignee, data in stats['by_assignee'].items():
            report += f"{assignee}: {data['open']} open / {data['total']} total\n"

        if output_path:
            with open(output_path, 'w') as f:
                f.write(report)

        return report


# Usage Example
if __name__ == "__main__":
    # Initialize manager
    manager = RFIManager(project_id="PROJECT-2026-001")

    # Create RFI
    rfi = manager.create_rfi(
        subject="Clarification on electrical panel location",
        question="""
        Drawing E-101 shows main electrical panel in Room 105,
        but specification Section 26 05 00 indicates utility room.
        Please confirm correct location and provide updated drawing
        if Room 105 is correct.
        """,
        submitted_by="Ivan Petrov",
        submitted_by_company="ABC Electrical",
        assigned_to="Architect",
        spec_section="26 05 00",
        drawing_ref="E-101",
        location="Building A, Floor 1",
        priority=RFIPriority.HIGH,
        days_for_response=5
    )

    print(f"Created: {rfi.rfi_number}")

    # Submit RFI
    manager.submit_rfi(rfi.rfi_number)

    # Respond to RFI
    manager.respond_to_rfi(
        rfi_number=rfi.rfi_number,
        response="""
        Room 105 is correct. Updated drawing E-101 Rev 2 attached.
        Specification will be updated in next addendum.
        """,
        response_by="John Architect",
        schedule_impact=True,
        schedule_days=2
    )

    # Close RFI
    manager.close_rfi(rfi.rfi_number)

    # Generate report
    print(manager.generate_report())
```

## n8n Integration

```yaml
name: RFI Notification Workflow
trigger:
  type: webhook
  path: /rfi-notification

steps:
  - parse_rfi:
      node: Code
      code: |
        return {
          rfi_number: $json.rfi_number,
          subject: $json.subject,
          assigned_to: $json.assigned_to,
          due_date: $json.date_required,
          priority: $json.priority
        };

  - get_recipient:
      node: Google Sheets
      operation: readRows
      sheet: Contacts
      filter: role = "={{$json.assigned_to}}"

  - send_email:
      node: Email
      to: "={{$json.email}}"
      subject: "[RFI {{$json.rfi_number}}] {{$json.subject}}"
      body: |
        New RFI requires your response:

        RFI #: {{$json.rfi_number}}
        Subject: {{$json.subject}}
        Priority: {{$json.priority}}
        Due Date: {{$json.due_date}}

        Please respond in the project portal.

  - send_telegram:
      node: Telegram
      operation: sendMessage
      chatId: "={{$json.telegram_id}}"
      text: |
        📋 *New RFI: {{$json.rfi_number}}*

        {{$json.subject}}

        Priority: {{$json.priority}}
        Due: {{$json.due_date}}

        [View in Portal]({{PROJECT_PORTAL_URL}}/rfi/{{$json.rfi_number}})
```

## Templates

### RFI Submission Template

```markdown
## REQUEST FOR INFORMATION

**RFI Number:** [Auto-generated]
**Date:** [Today]
**Project:** [Project Name]

### QUESTION
**Subject:** [Brief title - max 80 characters]

**Specification Section:** [CSI number]
**Drawing Reference:** [Drawing number(s)]
**Location:** [Building/Floor/Area]

**Question:**
[Detailed question - be specific about what clarification is needed]

**Suggested Resolution:**
[If you have a proposed solution, include it here]

### ATTACHMENTS
- [ ] Relevant drawing sections
- [ ] Photos of field conditions
- [ ] Specification excerpts

### IMPACT ASSESSMENT
- Estimated Cost Impact: [ ] Yes [ ] No  Amount: $_______
- Estimated Schedule Impact: [ ] Yes [ ] No  Days: _______
- Work Stoppage: [ ] Yes [ ] No

**Response Required By:** [Date - default +7 days]

---
Submitted by: [Name, Company]
```

---

*"A well-written RFI gets answered faster. Be specific, reference documents, and propose solutions."*

© datadrivenconstruction · MIT · datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction

Similar skills

All skills for Notes, tasks and projects →

From the same set156

The whole set →
safety-inspection-checklist Generates and runs digital safety inspection checklists for construction sites. Captures inspection data, photos, tracks defects, and produces compliance reports automatically. CX Codex +1 133installs schedule-delay-analyzer schedule-delay-analyzer is a skill that tracks project delays, their causes, and critical-path effects to estimate a time extension and review compensable costs. CX Codex +1 132installs subcontractor-payment-tracker subcontractor-payment-tracker tracks subcontractor invoices, retainage deductions, payment milestones, and lien waivers. Helpful for keeping construction financials in order. CX Codex +1 132installs pdf-report-generator The pdf-report-generator skill automates PDF report creation from construction project data. Combines charts, tables, and KPIs into a formatted document without manual assembly. CX Codex +1 132installs safety-compliance-checker safety-compliance-checker is a Claude Code skill that checks safety compliance on construction sites. It tracks PPE, zone access, and work at heights, and generates violation reports. CX Codex +1 131installs daily-report-generator The daily-report-generator skill pulls weather, crew hours, and progress data from your project sources and assembles them into a polished PDF report. Cuts manual reporting time from 45–60 minutes to about 9 minutes for review. CX Codex +1 130installs energy-simulation The energy-simulation skill models building energy performance, from heating and cooling loads to envelope checks and HVAC sizing. Use it when reviewing energy-code scenarios. CX Codex +1 129installs sensor-data-aggregator The sensor-data-aggregator skill collects, aggregates, and analyzes construction-site IoT sensor data in real time, detecting anomalies and triggering environmental alerts. CX Codex +1 129installs

Project sponsors

Companies that keep this analytics open