critical-path-analyzer — Claude Code skill: setup and features
critical-path-analyzer analyzes project schedule networks to calculate the critical path, determine float values, and identify near-critical tasks that risk delaying deadlines.
MIT 141 installs ★ 434 updated 2026-10-19
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer -a claude-codeWhat critical-path-analyzer does
The skill resolves project schedules using forward and backward network calculation passes. It topologically sorts activities, computes early and late boundary dates, and isolates operations with zero float that dictate the overall duration.
Activities can be added programmatically or imported straight from a pandas.DataFrame containing predecessor lists. Alongside the primary critical path, the code automatically flags near-critical tasks that have five or fewer days of total float.
Without python3 and the pandas package available in the environment, schedule calculations fail immediately. Install these dependencies beforehand so the agent can parse table data without interruptions.
What it helps with
- calculate the critical path across scheduled project tasks
- identify near-critical activities with five or fewer days of float
- compute early and late schedule boundaries using topological sorting
- import task dependency chains directly from a pandas DataFrame
Example prompts for the agent
- Analyze the critical path for the schedule in
schedule.csvand show zero-float activities - Run CPM analysis on these project tasks and highlight items with total float under 5 days
- Calculate early and late dates for our task network starting on September 1, 2025
How to install critical-path-analyzer
1Skills CLI (Vercel)
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer -a claude-code2Manually: put the files in place
~/.claude/skills/critical-path-analyzer/SKILL.mdCopy the whole skill folder; for one project use .claude/skills/critical-path-analyzer/
1Skills CLI (Vercel)
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer -a codex2Manually: put the files in place
.agents/skills/critical-path-analyzer/SKILL.mdFor all projects use ~/.agents/skills/
1Skills CLI (Vercel)
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer -a cursor2Manually: put the files in place
.cursor/skills/critical-path-analyzer/SKILL.mdCursor also reads .agents/skills/ and .claude/skills/
1GitHub CLI
gh skill install datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction 1_DDC_Toolkit/Schedule-Management/critical-path-analyzer2Manually: put the files in place
.github/skills/critical-path-analyzer/SKILL.md1Skills CLI (Vercel)
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer -a gemini-cli2Platform CLI
gemini skills install https://github.com/datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --path 1_DDC_Toolkit/Schedule-Management/critical-path-analyzerManually: put the files in place
.devin/skills/critical-path-analyzer/SKILL.mdThe legacy .windsurf/skills/ path still works
Skills CLI (Vercel)
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer -a opencodeClaude.ai
Zip the folder and upload it in Settings → Capabilities → Skills
Step by step, with commands for each platform: How to install skills in Claude Code: five ways
Questions about critical-path-analyzer
How do I install critical-path-analyzer in Claude Code?
Run npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill critical-path-analyzer -a claude-code. This installs the skill file into ~/.claude/skills/critical-path-analyzer/SKILL.md.
What does critical-path-analyzer do?
It processes activity dependencies using forward and backward CPM passes to determine total float, late dates, and activities driving the completion milestone.
What dependencies are required to run critical-path-analyzer?
The analyzer depends on a python3 binary alongside pandas and numpy packages to ingest tabular data and calculate network schedules.
Source text
SKILL.md · MIT
---
name: "critical-path-analyzer"
description: "Analyze project critical path from schedule data. Identify critical activities, calculate float, and assess schedule risk."
homepage: "https://datadrivenconstruction.io"
metadata: {"openclaw": {"emoji": "📅", "os": ["darwin", "linux", "win32"], "homepage": "https://datadrivenconstruction.io", "requires": {"bins": ["python3"]}}}
---
# Critical Path Analyzer
## Business Case
### Problem Statement
Schedule management requires understanding:
- Which activities are critical?
- How much float exists?
- What delays impact completion?
- Where to focus resources?
### Solution
Analyze schedule network to identify critical path, calculate float, and provide actionable schedule insights.
## Technical Implementation
```python
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Set
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict
class ActivityStatus(Enum):
NOT_STARTED = "not_started"
IN_PROGRESS = "in_progress"
COMPLETED = "completed"
DELAYED = "delayed"
@dataclass
class Activity:
activity_id: str
name: str
duration: int # days
predecessors: List[str]
early_start: int = 0
early_finish: int = 0
late_start: int = 0
late_finish: int = 0
total_float: int = 0
free_float: int = 0
is_critical: bool = False
status: ActivityStatus = ActivityStatus.NOT_STARTED
percent_complete: float = 0
actual_start: Optional[date] = None
actual_finish: Optional[date] = None
@dataclass
class CriticalPathResult:
critical_path: List[str]
project_duration: int
activities: Dict[str, Activity]
near_critical: List[str] # Float < 5 days
total_float_days: int
class CriticalPathAnalyzer:
"""Analyze project critical path."""
NEAR_CRITICAL_THRESHOLD = 5 # days
def __init__(self, project_start: date):
self.project_start = project_start
self.activities: Dict[str, Activity] = {}
def add_activity(self,
activity_id: str,
name: str,
duration: int,
predecessors: List[str] = None):
"""Add activity to network."""
self.activities[activity_id] = Activity(
activity_id=activity_id,
name=name,
duration=duration,
predecessors=predecessors or []
)
def import_from_dataframe(self, df: pd.DataFrame):
"""Import activities from DataFrame."""
for _, row in df.iterrows():
preds = row.get('predecessors', '')
if pd.isna(preds):
pred_list = []
else:
pred_list = [p.strip() for p in str(preds).split(',') if p.strip()]
self.add_activity(
activity_id=str(row['activity_id']),
name=row['name'],
duration=int(row['duration']),
predecessors=pred_list
)
def _forward_pass(self):
"""Calculate early start and early finish (forward pass)."""
# Topological sort
sorted_activities = self._topological_sort()
for activity_id in sorted_activities:
activity = self.activities[activity_id]
# Early start = max(early finish of all predecessors)
if not activity.predecessors:
activity.early_start = 0
else:
activity.early_start = max(
self.activities[pred].early_finish
for pred in activity.predecessors
if pred in self.activities
)
activity.early_finish = activity.early_start + activity.duration
def _backward_pass(self):
"""Calculate late start and late finish (backward pass)."""
# Find project duration
project_duration = max(a.early_finish for a in self.activities.values())
# Build successors map
successors = defaultdict(list)
for activity_id, activity in self.activities.items():
for pred in activity.predecessors:
if pred in self.activities:
successors[pred].append(activity_id)
# Reverse topological order
sorted_activities = self._topological_sort()[::-1]
for activity_id in sorted_activities:
activity = self.activities[activity_id]
# Late finish = min(late start of all successors)
if activity_id not in successors or not successors[activity_id]:
activity.late_finish = project_duration
else:
activity.late_finish = min(
self.activities[succ].late_start
for succ in successors[activity_id]
)
activity.late_start = activity.late_finish - activity.duration
# Calculate floats
activity.total_float = activity.late_start - activity.early_start
activity.is_critical = activity.total_float == 0
def _topological_sort(self) -> List[str]:
"""Topological sort of activities."""
visited = set()
result = []
def visit(activity_id: str):
if activity_id in visited:
return
visited.add(activity_id)
activity = self.activities.get(activity_id)
if activity:
for pred in activity.predecessors:
if pred in self.activities:
visit(pred)
result.append(activity_id)
for activity_id in self.activities:
visit(activity_id)
return result
def calculate_critical_path(self) -> CriticalPathResult:
"""Calculate critical path and all float values."""
self._forward_pass()
self._backward_pass()
# Find critical path
critical_activities = [
a.activity_id for a in self.activities.values()
if a.is_critical
]
# Near-critical activities
near_critical = [
a.activity_id for a in self.activities.values()
if 0 < a.total_float <= self.NEAR_CRITICAL_THRESHOLD
]
project_duration = max(a.early_finish for a in self.activities.values())
total_float = sum(a.total_float for a in self.activities.values())
return CriticalPathResult(
critical_path=critical_activities,
project_duration=project_duration,
activities=self.activities,
near_critical=near_critical,
total_float_days=total_float
)
def get_schedule_dates(self) -> pd.DataFrame:
"""Get schedule with dates."""
data = []
for activity in self.activities.values():
early_start_date = self.project_start + timedelta(days=activity.early_start)
early_finish_date = self.project_start + timedelta(days=activity.early_finish)
late_start_date = self.project_start + timedelta(days=activity.late_start)
late_finish_date = self.project_start + timedelta(days=activity.late_finish)
data.append({
'Activity ID': activity.activity_id,
'Name': activity.name,
'Duration': activity.duration,
'Early Start': early_start_date,
'Early Finish': early_finish_date,
'Late Start': late_start_date,
'Late Finish': late_finish_date,
'Total Float': activity.total_float,
'Critical': 'Yes' if activity.is_critical else 'No'
})
return pd.DataFrame(data)
def analyze_delay_impact(self,
activity_id: str,
delay_days: int) -> Dict[str, Any]:
"""Analyze impact of delay on project."""
activity = self.activities.get(activity_id)
if not activity:
return {}
absorbed_by_float = min(delay_days, activity.total_float)
project_delay = max(0, delay_days - activity.total_float)
# Find affected activities
affected = []
if project_delay > 0:
# Activities that could be affected (successors)
for a in self.activities.values():
if activity_id in a.predecessors:
affected.append(a.activity_id)
return {
'activity': activity_id,
'delay_days': delay_days,
'available_float': activity.total_float,
'absorbed_by_float': absorbed_by_float,
'project_delay': project_delay,
'affected_activities': affected,
'is_critical_delay': project_delay > 0
}
def suggest_acceleration(self,
target_reduction: int) -> List[Dict[str, Any]]:
"""Suggest activities to accelerate to meet target."""
result = self.calculate_critical_path()
suggestions = []
# Focus on critical activities
for activity_id in result.critical_path:
activity = self.activities[activity_id]
# Assume can reduce by 20% max
max_reduction = int(activity.duration * 0.2)
if max_reduction > 0:
suggestions.append({
'activity': activity_id,
'name': activity.name,
'current_duration': activity.duration,
'max_reduction': max_reduction,
'reason': 'Critical path activity'
})
# Sort by potential impact
return sorted(suggestions, key=lambda x: x['max_reduction'], reverse=True)
def export_analysis(self, output_path: str) -> str:
"""Export analysis to Excel."""
result = self.calculate_critical_path()
with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
# Summary
summary_df = pd.DataFrame([{
'Project Start': self.project_start,
'Project Duration': result.project_duration,
'Project Finish': self.project_start + timedelta(days=result.project_duration),
'Critical Activities': len(result.critical_path),
'Near-Critical Activities': len(result.near_critical),
'Total Float (days)': result.total_float_days
}])
summary_df.to_excel(writer, sheet_name='Summary', index=False)
# Schedule
schedule_df = self.get_schedule_dates()
schedule_df.to_excel(writer, sheet_name='Schedule', index=False)
# Critical Path
critical_df = pd.DataFrame([
{
'Activity': a_id,
'Name': self.activities[a_id].name,
'Duration': self.activities[a_id].duration
}
for a_id in result.critical_path
])
critical_df.to_excel(writer, sheet_name='Critical Path', index=False)
return output_path
```
## Quick Start
```python
from datetime import date
# Initialize analyzer
analyzer = CriticalPathAnalyzer(project_start=date(2024, 6, 1))
# Add activities
analyzer.add_activity("A", "Site Preparation", 10, [])
analyzer.add_activity("B", "Foundation Excavation", 15, ["A"])
analyzer.add_activity("C", "Foundation Concrete", 20, ["B"])
analyzer.add_activity("D", "Structural Steel", 30, ["C"])
analyzer.add_activity("E", "MEP Rough-in", 25, ["C"])
analyzer.add_activity("F", "Exterior Walls", 20, ["D"])
analyzer.add_activity("G", "Interior Finish", 15, ["E", "F"])
# Calculate critical path
result = analyzer.calculate_critical_path()
print(f"Project Duration: {result.project_duration} days")
print(f"Critical Path: {result.critical_path}")
```
## Common Use Cases
### 1. Analyze Delay Impact
```python
impact = analyzer.analyze_delay_impact("C", delay_days=5)
print(f"Project Delay: {impact['project_delay']} days")
```
### 2. Get Schedule Dates
```python
schedule = analyzer.get_schedule_dates()
print(schedule[['Activity ID', 'Early Start', 'Late Finish', 'Total Float']])
```
### 3. Acceleration Suggestions
```python
suggestions = analyzer.suggest_acceleration(target_reduction=10)
for s in suggestions:
print(f"{s['activity']}: can reduce {s['max_reduction']} days")
```
## Resources
- **DDC Book**: Chapter 4.2 - Schedule Analysis