tasks-parallel-analysis — Claude Code rule: what it does

The tasks-parallel-analysis rule sets checks for marking tasks in tasks.md as parallel work. Use it when an agent drafts an implementation plan and needs to account for dependencies.

MIT ★ 3,774 updated 2026-10-22

Install into Claude Code · Manually: put the files in place All methods and platforms ↓
.claude/rules/tasks-parallel-analysis.md
Open on GitHub

What tasks-parallel-analysis does

The rule allows a (P) marker only when a task has no pending data dependency, file or shared-resource conflict, or prerequisite approval. Earlier setup work must be complete, and _Boundary:_ annotations must show that the tasks cover separate components. Similar-looking tasks do not qualify on appearance alone.

Put (P) after the task number, outside the checkbox. Record dependencies and caveats in task details, and assess actionable subtasks rather than container tasks with no details of their own. When the requested mode is --sequential, omit all (P) markers. Shared resources can still cause merge or deployment conflicts, so the rule calls for checking them before marking work as parallel.

What it helps with

  • mark tasks in tasks.md that have no pending dependencies
  • separate component scopes with _Boundary:_ annotations
  • record a blocking dependency between tasks
  • remove (P) markers in sequential mode
  • check that each marked task can be tested independently

Example prompts for the agent

  • Draft tasks.md and mark (P) only where dependencies and component boundaries allow parallel work.
  • Review tasks.md for shared-file conflicts and add blocking dependencies to task details.
  • Create a sequential plan with --sequential and leave out every (P) marker.

How to install tasks-parallel-analysis

Manually: put the files in place

.claude/rules/tasks-parallel-analysis.md

The paths frontmatter field limits the files

Step by step, with commands for each platform: AGENTS.md vs CLAUDE.md: what they are and which one to use

Questions about tasks-parallel-analysis

How do I install tasks-parallel-analysis in Claude Code?

Add the rule file at .claude/rules/tasks-parallel-analysis.md.

What does tasks-parallel-analysis do?

It defines checks for marking tasks.md items with (P). The checks cover dependencies, shared resources, setup work, and component boundaries.

When should a task not get a (P) marker?

Leave it unmarked if it depends on pending work, shares files or mutable resources, or needs prior approval. In --sequential mode, omit all (P) markers.

Source text

tasks-parallel-analysis.md · MIT
# Parallel Task Analysis Rules

## Purpose
Provide a consistent way to identify implementation tasks that can be safely executed in parallel while generating `tasks.md`.

## Relationship to Task Ordering

`(P)` means: this task has no dependency on its immediately preceding peers and can run concurrently with them. The Task Ordering Principle (see tasks-generation.md) ensures Foundation-phase tasks run first, making Core-phase tasks the primary `(P)` candidates.

## When to Consider Tasks Parallel
Only mark a task as parallel-capable when **all** of the following are true:

1. **No data dependency** on pending tasks.
2. **No conflicting files or shared mutable resources** are touched.
3. **No prerequisite review/approval** from another task is required beforehand.
4. **Foundation work complete**: Environment/setup work needed by this task is already satisfied by earlier Foundation-phase tasks.
5. **Non-overlapping boundaries**: `_Boundary:_` annotations confirm tasks operate on separate components.

## Marking Convention
- Append `(P)` immediately after the numeric identifier for each qualifying task.
  - Example: `- [ ] 2.1 (P) Build background worker for emails`
- Apply `(P)` to both major tasks and sub-tasks when appropriate.
- If sequential execution is requested (e.g. via `--sequential` flag), omit `(P)` markers entirely.
- Keep `(P)` **outside** of checkbox brackets to avoid confusion with completion state.

## Grouping & Ordering Guidelines
- Group parallel tasks under the same parent whenever the work belongs to the same theme.
- List obvious prerequisites or caveats in the detail bullets (e.g., "Requires schema migration from 1.2").
- When two tasks look similar but are not parallel-safe, call out the blocking dependency explicitly.
- Skip marking container-only major tasks (those without their own actionable detail bullets) with `(P)`—evaluate parallel execution at the sub-task level instead.

## Quality Checklist
Before marking a task with `(P)`, ensure you have:

- Verified that running this task concurrently will not create merge or deployment conflicts.
- Confirmed `_Boundary:_` annotations show non-overlapping component scopes.
- Captured any shared state expectations in the detail bullets.
- Confirmed that the implementation can be tested independently.
- Added `_Depends: X.X_` if this `(P)` task still requires specific prior work from a different major-task group.

If any check fails, **do not** mark the task with `(P)` and explain the dependency in the task details.

© gotalab · MIT · gotalab/cc-sdd

Similar IDE rules

All IDE rules for Agent setup: memory, context, orchestration →

From the same set12

The whole set →
design-synthesis design-synthesis is a rule for analyzing gathered requirements before writing a design document. It uses generalization, build-or-adopt, and simplification to set the solution's scope. CX Codex +1 ★ 3,774repo stars steering-principles steering-principles defines standards for project memory files, capturing architecture patterns without cluttering context with exhaustive file catalogs. CX Codex +1 ★ 3,774repo stars requirements-review-gate The requirements-review-gate rule halts work and requires fixing the requirements draft before requirements.md is written. It validates scope coverage, EARS format compliance, and structural quality. CX Codex +1 ★ 3,774repo stars design-review-gate design-review-gate audits draft architectures before generating design.md. It links requirement IDs to concrete components and prevents speculative interfaces. CX Codex +1 ★ 3,774repo stars ears-format The ears-format rule formats acceptance criteria with EARS patterns. Use it when a specification needs clear conditions, subjects, and system responses. CX Codex +1 ★ 3,774repo stars design-discovery-full The design-discovery-full rule systematically maps requirements, existing code, technologies, and risks before design begins. It ensures architectural choices rest on facts rather than assumptions. CX Codex +1 ★ 3,774repo stars design-review design-review reviews technical design documents before coding starts and issues a GO/NO-GO verdict. Caps feedback at three critical issues tied directly to project requirements. CX Codex +1 ★ 3,774repo stars cc-sdd-new-agent The cc-sdd-new-agent skill guides a new coding-agent integration in cc-sdd, from official-format research and planning to implementation checks. CX Codex +1 ★ 3,774repo stars

Project sponsors

Companies that keep this analytics open