schedule-cost-link — Claude Code skill: schedule and cost integration

schedule-cost-link links construction schedule activities to budget line items, builds cash flow curves, and calculates earned value metrics.

MIT 117 installs ★ 434 updated 2026-10-19

Install into Claude Code · Skills CLI (Vercel) All methods and platforms ↓
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill schedule-cost-link -a claude-code
Open on GitHub

What schedule-cost-link does

The skill pairs a list of activities with budget codes and spreads costs across the project calendar. It includes a Python class ScheduleCostLinker with four cost distribution patterns: uniform, front-loaded, back-loaded, or bell curve. Attach a cost_code to each activity, and the skill outputs a cost-loaded schedule, daily cash flow profiles, and a set of EV metrics: BCWS, BCWP, SPI, CPI, EAC.

You need python3 in your PATH. Activity percent complete and actual costs go in through class methods. Pass start date, finish date, and duration; the output is a pandas DataFrame with schedule rows and cost columns.

What it helps with

  • pair schedule activities with budget cost codes
  • build a cost-loaded schedule with budget line items
  • plot a daily cash flow curve for the project
  • calculate earned value metrics: SPI, CPI, EAC
  • distribute costs uniformly, front-loaded, back-loaded, or bell-curved

Example prompts for the agent

  • Build a cost-loaded schedule from activities in activities.csv and link them to the budget in budget.xlsx
  • Plot the cash flow curve for a 2M budget project, spread costs uniformly
  • Calculate EV metrics as of today given activity percent complete and actual costs

How to install schedule-cost-link

1Skills CLI (Vercel)

npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill schedule-cost-link -a claude-code

2Manually: put the files in place

~/.claude/skills/schedule-cost-link/SKILL.md

Copy the whole skill folder; for one project use .claude/skills/schedule-cost-link/

Step by step, with commands for each platform: How to install skills in Claude Code: five ways

Questions about schedule-cost-link

How do I install schedule-cost-link in Claude Code?

Run npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill schedule-cost-link -a claude-code. The skill lands in ~/.claude/skills/schedule-cost-link/SKILL.md.

What does schedule-cost-link do?

It links schedule activities to budget line items, spreads costs over time with four distribution methods (uniform, front-loaded, back-loaded, bell curve), builds cost-loaded schedules and cash flow plots, and computes EV metrics.

What input does the skill need for EV calculation?

Budget per activity, start and finish dates, percent complete, and actual costs. All of this goes through methods of the ScheduleCostLinker class.

Source text

SKILL.md · MIT
---
name: "schedule-cost-link"
description: "Link schedule activities to cost items. Create cost-loaded schedules, generate cash flow curves, and track earned value."
homepage: "https://datadrivenconstruction.io"
metadata: {"openclaw": {"emoji": "📅", "os": ["darwin", "linux", "win32"], "homepage": "https://datadrivenconstruction.io", "requires": {"bins": ["python3"]}}}
---
# Schedule-Cost Linker

## Business Case

### Problem Statement
Integrating schedule and cost requires:
- Linking activities to budget items
- Creating cost-loaded schedules
- Generating cash flow forecasts
- Tracking earned value metrics

### Solution
Systematic linkage between schedule activities and cost data to enable integrated project control.

## Technical Implementation

```python
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Tuple
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict


class LoadingMethod(Enum):
    UNIFORM = "uniform"          # Even distribution
    FRONT_LOADED = "front_loaded"
    BACK_LOADED = "back_loaded"
    BELL_CURVE = "bell_curve"


@dataclass
class ScheduleActivity:
    activity_id: str
    name: str
    start_date: date
    finish_date: date
    duration: int
    percent_complete: float = 0


@dataclass
class CostItem:
    cost_code: str
    description: str
    budgeted_cost: float
    labor_cost: float
    material_cost: float
    equipment_cost: float


@dataclass
class ActivityCostLink:
    activity_id: str
    cost_code: str
    budgeted_cost: float
    loading_method: LoadingMethod


@dataclass
class EarnedValueMetrics:
    data_date: date
    bcws: float  # Budgeted Cost of Work Scheduled (PV)
    bcwp: float  # Budgeted Cost of Work Performed (EV)
    acwp: float  # Actual Cost of Work Performed (AC)
    sv: float    # Schedule Variance
    cv: float    # Cost Variance
    spi: float   # Schedule Performance Index
    cpi: float   # Cost Performance Index
    eac: float   # Estimate at Completion
    etc: float   # Estimate to Complete
    vac: float   # Variance at Completion


class ScheduleCostLinker:
    """Link schedule activities to cost items."""

    def __init__(self, project_name: str, budget_at_completion: float):
        self.project_name = project_name
        self.bac = budget_at_completion
        self.activities: Dict[str, ScheduleActivity] = {}
        self.cost_items: Dict[str, CostItem] = {}
        self.links: List[ActivityCostLink] = []
        self.actual_costs: Dict[str, float] = {}  # activity_id -> actual cost

    def add_activity(self,
                     activity_id: str,
                     name: str,
                     start_date: date,
                     finish_date: date,
                     percent_complete: float = 0):
        """Add schedule activity."""

        duration = (finish_date - start_date).days + 1

        self.activities[activity_id] = ScheduleActivity(
            activity_id=activity_id,
            name=name,
            start_date=start_date,
            finish_date=finish_date,
            duration=duration,
            percent_complete=percent_complete
        )

    def add_cost_item(self,
                      cost_code: str,
                      description: str,
                      budgeted_cost: float,
                      labor_pct: float = 0.4,
                      material_pct: float = 0.5,
                      equipment_pct: float = 0.1):
        """Add cost item."""

        self.cost_items[cost_code] = CostItem(
            cost_code=cost_code,
            description=description,
            budgeted_cost=budgeted_cost,
            labor_cost=budgeted_cost * labor_pct,
            material_cost=budgeted_cost * material_pct,
            equipment_cost=budgeted_cost * equipment_pct
        )

    def link_activity_cost(self,
                           activity_id: str,
                           cost_code: str,
                           loading_method: LoadingMethod = LoadingMethod.UNIFORM):
        """Link activity to cost item."""

        if activity_id not in self.activities:
            return

        cost_item = self.cost_items.get(cost_code)
        budgeted = cost_item.budgeted_cost if cost_item else 0

        self.links.append(ActivityCostLink(
            activity_id=activity_id,
            cost_code=cost_code,
            budgeted_cost=budgeted,
            loading_method=loading_method
        ))

    def record_actual_cost(self, activity_id: str, actual_cost: float):
        """Record actual cost for activity."""
        self.actual_costs[activity_id] = actual_cost

    def _distribute_cost(self,
                          cost: float,
                          start_date: date,
                          duration: int,
                          method: LoadingMethod) -> Dict[date, float]:
        """Distribute cost over activity duration."""

        daily_costs = {}

        if duration <= 0:
            return {start_date: cost}

        if method == LoadingMethod.UNIFORM:
            daily = cost / duration
            for i in range(duration):
                daily_costs[start_date + timedelta(days=i)] = daily

        elif method == LoadingMethod.FRONT_LOADED:
            total_weight = sum(range(duration, 0, -1))
            for i in range(duration):
                weight = (duration - i) / total_weight
                daily_costs[start_date + timedelta(days=i)] = cost * weight

        elif method == LoadingMethod.BACK_LOADED:
            total_weight = sum(range(1, duration + 1))
            for i in range(duration):
                weight = (i + 1) / total_weight
                daily_costs[start_date + timedelta(days=i)] = cost * weight

        elif method == LoadingMethod.BELL_CURVE:
            # Simplified bell curve
            mid = duration / 2
            for i in range(duration):
                distance = abs(i - mid)
                weight = 1 - (distance / mid) * 0.5
                daily_costs[start_date + timedelta(days=i)] = cost * weight / duration

        return daily_costs

    def generate_cost_loaded_schedule(self) -> pd.DataFrame:
        """Generate cost-loaded schedule."""

        data = []

        for link in self.links:
            activity = self.activities.get(link.activity_id)
            cost_item = self.cost_items.get(link.cost_code)

            if activity and cost_item:
                data.append({
                    'Activity ID': activity.activity_id,
                    'Activity Name': activity.name,
                    'Cost Code': link.cost_code,
                    'Description': cost_item.description,
                    'Start': activity.start_date,
                    'Finish': activity.finish_date,
                    'Duration': activity.duration,
                    'Budget': link.budgeted_cost,
                    '% Complete': activity.percent_complete,
                    'Earned Value': link.budgeted_cost * activity.percent_complete / 100,
                    'Loading': link.loading_method.value
                })

        return pd.DataFrame(data)

    def generate_cash_flow(self,
                           project_start: date = None,
                           project_end: date = None) -> pd.DataFrame:
        """Generate cash flow curve."""

        if not self.links:
            return pd.DataFrame()

        # Get date range
        if project_start is None:
            project_start = min(self.activities[l.activity_id].start_date for l in self.links)
        if project_end is None:
            project_end = max(self.activities[l.activity_id].finish_date for l in self.links)

        # Aggregate daily costs
        daily_totals = defaultdict(float)

        for link in self.links:
            activity = self.activities.get(link.activity_id)
            if not activity:
                continue

            daily_costs = self._distribute_cost(
                link.budgeted_cost,
                activity.start_date,
                activity.duration,
                link.loading_method
            )

            for day, cost in daily_costs.items():
                daily_totals[day] += cost

        # Build cash flow data
        data = []
        cumulative = 0
        current = project_start

        while current <= project_end:
            daily = daily_totals.get(current, 0)
            cumulative += daily

            data.append({
                'Date': current,
                'Daily': round(daily, 2),
                'Cumulative': round(cumulative, 2),
                'Cumulative %': round(cumulative / self.bac * 100, 1) if self.bac > 0 else 0
            })

            current += timedelta(days=1)

        return pd.DataFrame(data)

    def calculate_earned_value(self, data_date: date) -> EarnedValueMetrics:
        """Calculate earned value metrics at data date."""

        # BCWS - Planned Value through data date
        bcws = 0
        for link in self.links:
            activity = self.activities.get(link.activity_id)
            if not activity:
                continue

            daily_costs = self._distribute_cost(
                link.budgeted_cost,
                activity.start_date,
                activity.duration,
                link.loading_method
            )

            for day, cost in daily_costs.items():
                if day <= data_date:
                    bcws += cost

        # BCWP - Earned Value (budget * % complete)
        bcwp = 0
        for link in self.links:
            activity = self.activities.get(link.activity_id)
            if activity:
                bcwp += link.budgeted_cost * activity.percent_complete / 100

        # ACWP - Actual Cost
        acwp = sum(self.actual_costs.values())

        # Variances
        sv = bcwp - bcws
        cv = bcwp - acwp

        # Indices
        spi = bcwp / bcws if bcws > 0 else 0
        cpi = bcwp / acwp if acwp > 0 else 0

        # Forecasts
        eac = self.bac / cpi if cpi > 0 else self.bac
        etc = eac - acwp
        vac = self.bac - eac

        return EarnedValueMetrics(
            data_date=data_date,
            bcws=round(bcws, 2),
            bcwp=round(bcwp, 2),
            acwp=round(acwp, 2),
            sv=round(sv, 2),
            cv=round(cv, 2),
            spi=round(spi, 2),
            cpi=round(cpi, 2),
            eac=round(eac, 2),
            etc=round(etc, 2),
            vac=round(vac, 2)
        )

    def get_monthly_cash_flow(self) -> pd.DataFrame:
        """Aggregate cash flow by month."""

        daily = self.generate_cash_flow()
        if daily.empty:
            return pd.DataFrame()

        daily['Month'] = pd.to_datetime(daily['Date']).dt.to_period('M')
        monthly = daily.groupby('Month').agg({
            'Daily': 'sum',
            'Cumulative': 'last'
        }).reset_index()

        monthly.columns = ['Month', 'Monthly Cost', 'Cumulative']
        return monthly

    def export_to_excel(self, output_path: str) -> str:
        """Export integrated data to Excel."""

        with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
            # Cost-loaded schedule
            schedule = self.generate_cost_loaded_schedule()
            schedule.to_excel(writer, sheet_name='Cost-Loaded Schedule', index=False)

            # Cash flow
            cash_flow = self.generate_cash_flow()
            if not cash_flow.empty:
                cash_flow.to_excel(writer, sheet_name='Cash Flow', index=False)

            # Monthly
            monthly = self.get_monthly_cash_flow()
            if not monthly.empty:
                monthly.to_excel(writer, sheet_name='Monthly', index=False)

            # Earned Value
            evm = self.calculate_earned_value(date.today())
            evm_df = pd.DataFrame([{
                'Data Date': evm.data_date,
                'BCWS (PV)': evm.bcws,
                'BCWP (EV)': evm.bcwp,
                'ACWP (AC)': evm.acwp,
                'SV': evm.sv,
                'CV': evm.cv,
                'SPI': evm.spi,
                'CPI': evm.cpi,
                'EAC': evm.eac,
                'ETC': evm.etc,
                'VAC': evm.vac
            }])
            evm_df.to_excel(writer, sheet_name='Earned Value', index=False)

        return output_path
```

## Quick Start

```python
from datetime import date, timedelta

# Initialize linker
linker = ScheduleCostLinker("Office Building", budget_at_completion=5000000)

# Add activities
linker.add_activity("A-001", "Foundation", date(2024, 6, 1), date(2024, 6, 30), percent_complete=100)
linker.add_activity("A-002", "Structure", date(2024, 7, 1), date(2024, 9, 30), percent_complete=60)
linker.add_activity("A-003", "MEP", date(2024, 8, 1), date(2024, 11, 30), percent_complete=30)

# Add cost items
linker.add_cost_item("01-FOUND", "Foundation Work", 500000)
linker.add_cost_item("02-STRUCT", "Structural Work", 2000000)
linker.add_cost_item("03-MEP", "MEP Systems", 1500000)

# Link
linker.link_activity_cost("A-001", "01-FOUND")
linker.link_activity_cost("A-002", "02-STRUCT", LoadingMethod.BELL_CURVE)
linker.link_activity_cost("A-003", "03-MEP", LoadingMethod.BACK_LOADED)

# Record actuals
linker.record_actual_cost("A-001", 520000)
linker.record_actual_cost("A-002", 1300000)
```

## Common Use Cases

### 1. Earned Value Analysis
```python
evm = linker.calculate_earned_value(date.today())
print(f"CPI: {evm.cpi}")
print(f"SPI: {evm.spi}")
print(f"EAC: ${evm.eac:,.2f}")
```

### 2. Cash Flow Forecast
```python
cash_flow = linker.generate_cash_flow()
print(cash_flow.tail(10))
```

### 3. Monthly Breakdown
```python
monthly = linker.get_monthly_cash_flow()
print(monthly)
```

## Resources
- **DDC Book**: Chapter 4.2 - Schedule-Cost Integration

© datadrivenconstruction · MIT · datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction

Similar skills

All skills for Agent setup: memory, context, orchestration →

From the same set156

The whole set →
data-evolution-analysis data-evolution-analysis evaluates digital maturity in construction firms based on the DDC methodology. Identifies gaps across data flows and builds a transition roadmap. CX Codex +1 118installs semantic-search-cwicr semantic-search-cwicr finds similar construction work items in DDC CWICR cost databases using natural-language vector search. Covers 8 national bases in 26 languages. CX Codex +1 118installs cwicr-risk-calculator cwicr-risk-calculator calculates risk-adjusted construction cost estimates and contingency buffers using Monte Carlo simulation. CX Codex +1 118installs nobim-image-generator The nobim-image-generator Claude Code skill creates visuals from BIM data without BIM software. It runs on requests to generate images or diagrams from Revit or IFC models. CX Codex +1 117installs payment-application-generator payment-application-generator generates AIA-style payment applications: tracks schedule of values, calculates retention, and produces payment documentation. CX Codex +1 117installs erp-integration-analysis The erp-integration-analysis skill maps data flows between ERP modules in construction organizations, then flags bottlenecks and suggests changes. Use it to review how systems connect. CX Codex +1 117installs etl-pipeline etl-pipeline is a skill for building construction-data workflows that extract, clean, validate, aggregate, and send results to files, databases, APIs, or dashboards. CX Codex +1 117installs payment-application-processor payment-application-processor — a skill that processes construction payment applications: validates schedule of values, calculates retainage, tracks payment status, and generates G702/G703 forms. Requires Python 3. CX Codex +1 117installs