duration-prediction — Claude Code skill: project timelines

The duration-prediction Claude Code skill estimates construction project durations with k-NN and regression, using records from past projects. It runs when an agent is asked to forecast a new project's timeline from comparable work.

MIT 115 installs ★ 434 updated 2026-10-19

Install into Claude Code · Skills CLI (Vercel) All methods and platforms ↓
npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill duration-prediction -a claude-code
Open on GitHub

What duration-prediction does

The skill estimates a project's duration from its features and completed-project records. It compares project type, floor area, storeys, complexity, location, basement status, and renovation status to find similar jobs. Standard k-NN averages the nearest projects' durations; the weighted version gives closer matches more influence.

The code also includes a project-type baseline, used when no matching historical records are found. Results contain a duration estimate, an interval, similar project IDs, and the selected model. Running the data-loading code requires Python 3, pandas, and numpy; estimates based on comparable projects need historical project records.

What it helps with

  • forecast a construction timeline from completed projects
  • compare expected durations for projects of the same type
  • retrieve a duration interval and IDs of comparable projects

Example prompts for the agent

  • Estimate the timeline for this new office project from historical records.
  • Compare this residential project with completed projects of the same type.
  • Predict the project duration and return comparable project IDs.

How to install duration-prediction

1Skills CLI (Vercel)

npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill duration-prediction -a claude-code

2Manually: put the files in place

~/.claude/skills/duration-prediction/SKILL.md

Copy the whole skill folder; for one project use .claude/skills/duration-prediction/

Step by step, with commands for each platform: How to install skills in Claude Code: five ways

Questions about duration-prediction

How do I install duration-prediction in Claude Code?

Run npx skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill duration-prediction -a claude-code. The skill file is at ~/.claude/skills/duration-prediction/SKILL.md.

What does duration-prediction do?

It forecasts construction project duration from historical project data. Its k-NN methods find comparable jobs and return an estimate, an interval, and the IDs of those projects.

What does duration-prediction need to run?

The data-loading code requires Python 3, pandas, and numpy. Historical records with actual project durations are needed for estimates based on comparable jobs.

Source text

SKILL.md · MIT
---
name: "duration-prediction"
description: "Predict project duration using k-NN and regression. Estimate timeline based on similar historical projects."
homepage: "https://datadrivenconstruction.io"
metadata: {"openclaw": {"emoji": "🤖", "os": ["darwin", "linux", "win32"], "homepage": "https://datadrivenconstruction.io", "requires": {"bins": ["python3"]}}}
---
# Duration Prediction

## Business Case

### Problem Statement
Project duration estimation challenges:
- Subjective expert estimates
- Lack of historical benchmarking
- Inaccurate early-stage predictions
- Difficulty comparing similar projects

### Solution
Machine learning-based duration prediction using k-Nearest Neighbors and regression models trained on historical project data.

## Technical Implementation

```python
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Tuple
from dataclasses import dataclass, field
from datetime import date
from enum import Enum
import math


class ModelType(Enum):
    KNN = "knn"
    LINEAR_REGRESSION = "linear_regression"
    WEIGHTED_KNN = "weighted_knn"


class ProjectType(Enum):
    OFFICE = "office"
    RESIDENTIAL = "residential"
    INDUSTRIAL = "industrial"
    RETAIL = "retail"
    HEALTHCARE = "healthcare"
    EDUCATION = "education"


@dataclass
class ProjectFeatures:
    project_id: str
    project_type: ProjectType
    size_sf: float
    floors: int
    complexity: int  # 1-5
    location_factor: float  # Cost adjustment factor
    has_basement: bool = False
    is_renovation: bool = False
    actual_duration: Optional[int] = None  # Days


@dataclass
class PredictionResult:
    predicted_duration: int
    confidence_interval: Tuple[int, int]
    similar_projects: List[str]
    model_used: ModelType
    features_importance: Dict[str, float]


class DurationPredictor:
    """Predict project duration using ML techniques."""

    def __init__(self):
        self.training_data: List[ProjectFeatures] = []
        self.feature_weights: Dict[str, float] = {
            'size_sf': 0.30,
            'floors': 0.15,
            'complexity': 0.25,
            'location_factor': 0.10,
            'has_basement': 0.10,
            'is_renovation': 0.10
        }
        self.type_baseline_days: Dict[ProjectType, Dict[str, float]] = {
            ProjectType.OFFICE: {'base': 300, 'per_1000sf': 0.5},
            ProjectType.RESIDENTIAL: {'base': 240, 'per_1000sf': 0.4},
            ProjectType.INDUSTRIAL: {'base': 180, 'per_1000sf': 0.3},
            ProjectType.RETAIL: {'base': 200, 'per_1000sf': 0.35},
            ProjectType.HEALTHCARE: {'base': 400, 'per_1000sf': 0.6},
            ProjectType.EDUCATION: {'base': 320, 'per_1000sf': 0.45}
        }

    def add_training_project(self, project: ProjectFeatures):
        """Add project to training dataset."""
        if project.actual_duration is not None:
            self.training_data.append(project)

    def load_training_data(self, df: pd.DataFrame):
        """Load training data from DataFrame."""

        for _, row in df.iterrows():
            project = ProjectFeatures(
                project_id=str(row['project_id']),
                project_type=ProjectType(row['project_type'].lower()),
                size_sf=float(row['size_sf']),
                floors=int(row['floors']),
                complexity=int(row['complexity']),
                location_factor=float(row.get('location_factor', 1.0)),
                has_basement=bool(row.get('has_basement', False)),
                is_renovation=bool(row.get('is_renovation', False)),
                actual_duration=int(row['actual_duration'])
            )
            self.add_training_project(project)

    def _extract_features(self, project: ProjectFeatures) -> np.ndarray:
        """Extract feature vector from project."""

        return np.array([
            project.size_sf / 10000,  # Normalize to 10k SF
            project.floors,
            project.complexity,
            project.location_factor,
            1 if project.has_basement else 0,
            1 if project.is_renovation else 0
        ])

    def _calculate_distance(self, features1: np.ndarray,
                            features2: np.ndarray) -> float:
        """Calculate weighted Euclidean distance."""

        weights = np.array(list(self.feature_weights.values()))
        diff = (features1 - features2) ** 2
        weighted_diff = diff * weights
        return math.sqrt(np.sum(weighted_diff))

    def _find_k_nearest(self, target: ProjectFeatures, k: int = 5,
                        same_type: bool = True) -> List[Tuple[ProjectFeatures, float]]:
        """Find k nearest neighbors."""

        target_features = self._extract_features(target)
        distances = []

        for project in self.training_data:
            if same_type and project.project_type != target.project_type:
                continue

            proj_features = self._extract_features(project)
            distance = self._calculate_distance(target_features, proj_features)
            distances.append((project, distance))

        distances.sort(key=lambda x: x[1])
        return distances[:k]

    def predict_knn(self, target: ProjectFeatures, k: int = 5) -> PredictionResult:
        """Predict duration using k-NN."""

        nearest = self._find_k_nearest(target, k)

        if not nearest:
            # Fall back to baseline
            return self._predict_baseline(target)

        # Simple average of k nearest
        durations = [p.actual_duration for p, _ in nearest]
        predicted = int(np.mean(durations))

        # Confidence interval (using std dev)
        std = np.std(durations)
        lower = int(predicted - 1.96 * std)
        upper = int(predicted + 1.96 * std)

        return PredictionResult(
            predicted_duration=predicted,
            confidence_interval=(max(1, lower), upper),
            similar_projects=[p.project_id for p, _ in nearest],
            model_used=ModelType.KNN,
            features_importance=self.feature_weights
        )

    def predict_weighted_knn(self, target: ProjectFeatures, k: int = 5) -> PredictionResult:
        """Predict duration using distance-weighted k-NN."""

        nearest = self._find_k_nearest(target, k)

        if not nearest:
            return self._predict_baseline(target)

        # Inverse distance weighting
        total_weight = 0
        weighted_sum = 0

        for project, distance in nearest:
            weight = 1 / (distance + 0.001)  # Add small value to avoid division by zero
            weighted_sum += project.actual_duration * weight
            total_weight += weight

        predicted = int(weighted_sum / total_weight)

        # Confidence interval
        durations = [p.actual_duration for p, _ in nearest]
        std = np.std(durations)
        lower = int(predicted - 1.96 * std)
        upper = int(predicted + 1.96 * std)

        return PredictionResult(
            predicted_duration=predicted,
            confidence_interval=(max(1, lower), upper),
            similar_projects=[p.project_id for p, _ in nearest],
            model_used=ModelType.WEIGHTED_KNN,
            features_importance=self.feature_weights
        )

    def predict_regression(self, target: ProjectFeatures) -> PredictionResult:
        """Predict duration using linear regression."""

        if len(self.training_data) < 3:
            return self._predict_baseline(target)

        # Filter by project type
        same_type = [p for p in self.training_data if p.project_type == target.project_type]

        if len(same_type) < 3:
            same_type = self.training_data

        # Build feature matrix and target vector
        X = np.array([self._extract_features(p) for p in same_type])
        y = np.array([p.actual_duration for p in same_type])

        # Simple linear regression using normal equations
        X_with_intercept = np.column_stack([np.ones(len(X)), X])

        try:
            # beta = (X'X)^-1 X'y
            XtX = X_with_intercept.T @ X_with_intercept
            XtX_inv = np.linalg.inv(XtX)
            beta = XtX_inv @ X_with_intercept.T @ y
        except np.linalg.LinAlgError:
            return self._predict_baseline(target)

        # Predict
        target_features = self._extract_features(target)
        target_with_intercept = np.array([1] + list(target_features))
        predicted = int(target_features @ beta[1:] + beta[0])

        # Calculate residuals for confidence interval
        y_pred = X_with_intercept @ beta
        residuals = y - y_pred
        rmse = math.sqrt(np.mean(residuals ** 2))

        return PredictionResult(
            predicted_duration=max(1, predicted),
            confidence_interval=(max(1, int(predicted - 1.96 * rmse)),
                               int(predicted + 1.96 * rmse)),
            similar_projects=[p.project_id for p in same_type[:5]],
            model_used=ModelType.LINEAR_REGRESSION,
            features_importance=dict(zip(self.feature_weights.keys(),
                                        [abs(b) / sum(abs(beta[1:])) for b in beta[1:]]))
        )

    def _predict_baseline(self, target: ProjectFeatures) -> PredictionResult:
        """Fall back to baseline prediction."""

        baseline = self.type_baseline_days.get(target.project_type,
                                                {'base': 250, 'per_1000sf': 0.4})

        predicted = int(baseline['base'] +
                       (target.size_sf / 1000) * baseline['per_1000sf'] * 30)

        # Adjustments
        if target.complexity > 3:
            predicted = int(predicted * (1 + (target.complexity - 3) * 0.1))
        if target.has_basement:
            predicted = int(predicted * 1.1)
        if target.is_renovation:
            predicted = int(predicted * 1.2)

        predicted = int(predicted * target.location_factor)

        return PredictionResult(
            predicted_duration=predicted,
            confidence_interval=(int(predicted * 0.8), int(predicted * 1.2)),
            similar_projects=[],
            model_used=ModelType.LINEAR_REGRESSION,
            features_importance=self.feature_weights
        )

    def predict(self, target: ProjectFeatures,
                model: ModelType = ModelType.WEIGHTED_KNN,
                k: int = 5) -> PredictionResult:
        """Predict duration using specified model."""

        if model == ModelType.KNN:
            return self.predict_knn(target, k)
        elif model == ModelType.WEIGHTED_KNN:
            return self.predict_weighted_knn(target, k)
        elif model == ModelType.LINEAR_REGRESSION:
            return self.predict_regression(target)

        return self._predict_baseline(target)

    def evaluate_model(self, test_data: List[ProjectFeatures],
                       model: ModelType = ModelType.WEIGHTED_KNN) -> Dict[str, float]:
        """Evaluate model performance."""

        actuals = []
        predictions = []

        for project in test_data:
            if project.actual_duration is None:
                continue

            result = self.predict(project, model)
            actuals.append(project.actual_duration)
            predictions.append(result.predicted_duration)

        if not actuals:
            return {}

        actuals = np.array(actuals)
        predictions = np.array(predictions)

        mae = np.mean(np.abs(actuals - predictions))
        mape = np.mean(np.abs((actuals - predictions) / actuals)) * 100
        rmse = math.sqrt(np.mean((actuals - predictions) ** 2))

        return {
            'mae': round(mae, 1),
            'mape': round(mape, 1),
            'rmse': round(rmse, 1),
            'samples': len(actuals)
        }

    def get_similar_projects(self, target: ProjectFeatures, n: int = 10) -> pd.DataFrame:
        """Get most similar projects."""

        nearest = self._find_k_nearest(target, k=n, same_type=False)

        data = [{
            'Project ID': p.project_id,
            'Type': p.project_type.value,
            'Size (SF)': p.size_sf,
            'Floors': p.floors,
            'Complexity': p.complexity,
            'Duration (days)': p.actual_duration,
            'Distance': round(d, 3)
        } for p, d in nearest]

        return pd.DataFrame(data)
```

## Quick Start

```python
# Create predictor
predictor = DurationPredictor()

# Add training data
training_projects = [
    ProjectFeatures("P001", ProjectType.OFFICE, 50000, 10, 3, 1.0, True, False, 365),
    ProjectFeatures("P002", ProjectType.OFFICE, 75000, 15, 4, 1.1, True, False, 450),
    ProjectFeatures("P003", ProjectType.OFFICE, 30000, 5, 2, 0.9, False, False, 280),
    ProjectFeatures("P004", ProjectType.OFFICE, 60000, 12, 3, 1.0, True, False, 390),
]

for p in training_projects:
    predictor.add_training_project(p)

# Predict for new project
new_project = ProjectFeatures(
    project_id="NEW-001",
    project_type=ProjectType.OFFICE,
    size_sf=55000,
    floors=11,
    complexity=3,
    location_factor=1.0,
    has_basement=True,
    is_renovation=False
)

result = predictor.predict(new_project, ModelType.WEIGHTED_KNN)
print(f"Predicted duration: {result.predicted_duration} days")
print(f"Confidence interval: {result.confidence_interval}")
print(f"Similar projects: {result.similar_projects}")
```

## Common Use Cases

### 1. Compare Models
```python
knn_result = predictor.predict(new_project, ModelType.KNN)
weighted_result = predictor.predict(new_project, ModelType.WEIGHTED_KNN)
regression_result = predictor.predict(new_project, ModelType.LINEAR_REGRESSION)

print(f"k-NN: {knn_result.predicted_duration}")
print(f"Weighted k-NN: {weighted_result.predicted_duration}")
print(f"Regression: {regression_result.predicted_duration}")
```

### 2. Model Evaluation
```python
metrics = predictor.evaluate_model(test_data, ModelType.WEIGHTED_KNN)
print(f"MAE: {metrics['mae']} days")
print(f"MAPE: {metrics['mape']}%")
```

### 3. Find Similar Projects
```python
similar = predictor.get_similar_projects(new_project, n=5)
print(similar)
```

## Resources
- **DDC Book**: Chapter 4.5 - Future: Predictions and Machine Learning
- **scikit-learn**: https://scikit-learn.org/
- **Website**: https://datadrivenconstruction.io

© datadrivenconstruction · MIT · datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction

Similar skills

All skills for AI and ML →
downtrend-duration-analyzer tradermonty downtrend-duration-analyzer — a skill for Claude Code and five other platforms that processes historical price data to find peak-to-trough periods and outputs interactive HTML histograms broken down by sector and market cap tier. CX Codex +1 3,400installs llmquant-prediction-markets LLMQuant llmquant-prediction-markets is a Claude Code skill that routes prediction-market research requests. It handles event probabilities, settlement terms, cross-venue pricing, and arbitrage checks. CX Codex +1 523installs tooluniverse-immunotherapy-response-prediction mims-harvard tooluniverse-immunotherapy-response-prediction scores a tumor profile against TMB, MSI, PD-L1, HLA and immune gene expression, then names specific checkpoint inhibitors and flags resistance risk. CX Codex +1 366installs prediction-market-strategy agiprolabs prediction-market-strategy is a Claude Code skill for selecting binary prediction-market trades by net edge, sizing positions, and backtesting. CX Codex +1 366installs tooluniverse-admet-prediction mims-harvard The tooluniverse-admet-prediction Claude Code skill profiles drug candidates by ADMET properties. It helps discard compounds likely to fail before wet-lab work. CX Codex +1 245installs prediction-market-live-ops agiprolabs prediction-market-live-ops — a skill for automated trading on prediction markets (Kalshi). Combines backtest methodology, live-execution safety rails, and hypothesis-falsification protocols derived from a real live-money campaign. CX Codex +1 194installs

From the same set156

The whole set →
retention-tracker The retention-tracker Claude Code skill tracks retainage across construction projects. It records amounts held for subcontractors and follows release conditions. CX Codex +1 115installs data-profiler data-profiler — a skill for Claude Code that inspects construction datasets. It scans tables for missing fields, duplicates, cost outliers, and industry-specific identifiers prior to ETL runs. CX Codex +1 115installs data-anomaly-detector The data-anomaly-detector Claude Code skill detects unusual values in construction data with statistical and ML-based methods. It flags cost outliers, schedule shifts, and productivity spikes. CX Codex +1 115installs productivity-analyzer productivity-analyzer — a skill for Claude Code analyzes labor output rates using jobsite progress logs. Compares planned against actual progress and detects efficiency trends. CX Codex +1 115installs voice-to-report The voice-to-report skill for Claude Code converts voice recordings into structured construction reports. It activates when field workers need to quickly log site data, such as daily updates or safety observations. CX Codex +1 115installs progress-monitoring-cv The progress-monitoring-cv skill reads site photos and drone imagery to estimate construction progress, flag safety concerns, and compare built work with BIM plans. CX Codex +1 115installs cwicr-data-loader cwicr-data-loader is a Claude Code skill for loading the DDC CWICR database from Parquet, Excel, CSV, and Qdrant. It provides automatic schema detection and type validation. CX Codex +1 115installs open-data-integrator open-data-integrator connects open construction datasets to your coding agent: material cost indices, labor benchmarks, and weather records. CX Codex +1 115installs

Project sponsors

Companies that keep this analytics open