retrospective — Claude Code skill: what it does, how to install

Generates sprint and milestone retrospectives from task plans, git commits, and blockers. Helps capture action items for upcoming iterations.

Install into Claude Code · Skills CLI (Vercel) All methods and platforms ↓
npx skills add Donchitos/Claude-Code-Game-Studios --skill retrospective -a claude-code
Open on GitHub

What retrospective does

This skill evaluates sprint or milestone outcomes by comparing planned work against actual delivery. It reads sprint plans from production/sprints/ or milestone goals from production/milestones/, then checks production/sprint-status.yaml alongside git log. The report breaks down completed, modified, carryover, and unplanned tasks.

The skill enforces an explicit input check. If required artifacts are missing, it refuses to guess velocity and marks sections as NOT ASSESSED — NO DATA. It also checks the repository for TODO, FIXME, and HACK comment counts to track technical debt over time. If your project lacks sprint files in the production/ directory, you must supply details manually or abort the run.

What it helps with

  • Reconcile finished deliverables against the original sprint plan
  • Extract reported blockers into next-sprint action items
  • Track TODO and FIXME comment counts across the codebase
  • Compare velocity trends against previous retrospectives

Example prompts for the agent

  • /retrospective sprint-1
  • /retrospective milestone-alpha
  • /retrospective

How to install retrospective

1Skills CLI (Vercel)

npx skills add Donchitos/Claude-Code-Game-Studios --skill retrospective -a claude-code

2Manually: put the files in place

~/.claude/skills/retrospective/SKILL.md

Copy the whole skill folder; for one project use .claude/skills/retrospective/

Step by step, with commands for each platform: How to install skills in Claude Code: five ways

Questions about retrospective

How do I install retrospective in Claude Code?

Run npx skills add Donchitos/Claude-Code-Game-Studios --skill retrospective -a claude-code. The skill file will be placed in .claude/skills/retrospective/SKILL.md.

What does retrospective do?

It parses sprint plans and status YAML files, correlates them with git commits, and outputs an iteration retrospective. It documents carryover tasks, blockers, and technical debt trends.

What happens if sprint plans are missing?

The skill stops and records NOT ASSESSED — NO DATA instead of hallucinating metrics. It then prompts you to provide task details manually, review closed stories, or cancel.

Source text

SKILL.md · MIT
---
name: retrospective
description: "Sprint or milestone retrospective from completed work, velocity, blockers. Actionable insights for the next iteration."
argument-hint: "[sprint-N|milestone-name]"
user-invocable: true
allowed-tools: Read, Glob, Grep, Write, AskUserQuestion, Bash(bash "*/.claude/skills/retrospective/../../hooks/yaml-helper.sh" resolve_config *), Bash(git log *)
model: sonnet
---

!`bash "${CLAUDE_SKILL_DIR}/../../hooks/yaml-helper.sh" resolve_config --keys automation,workflow,qa.level`

# Retrospective



Every `AskUserQuestion` call follows `.claude/docs/automation-modes.md`
(collaborative asks always · guided major-only · autonomous logs and proceeds;
`automation_always_ask` categories always prompt).

## Insufficient input — check this before producing any report

**If the inputs this skill needs do not exist, the answer is "could not run" —
not a filled-in report.** Check first, and stop if the check fails.

1. List the inputs this skill reads (data files, prior reports, profiler output,
   test results, registries, source code).
2. For each, record `FOUND` or `ABSENT` — not "assumed present".
3. If any input required for a section is ABSENT, that section is
   **`NOT ASSESSED — NO DATA`**. Do not estimate it, do not infer it from an
   adjacent artifact, and do not leave a mandated cell to be filled by whoever
   reads the template next.
4. If **every** required input is ABSENT, stop and report
   **`NOT ASSESSED — NO DATA`** as the whole verdict, naming what was missing and
   which skill produces it.

**A verdict of `NOT ASSESSED` is a success.** It is the correct, useful answer to
"what does the data say?" when there is no data. The failure mode this prevents is
specific: a report whose verdict enum has no "could not run" state produces
**false clean passes** — an asset audit returning COMPLIANT on a project with no
assets and no standards, or a performance profile reporting ">99% headroom against
a 16.67ms budget" with zero profiler data and no budget ever set.

**Absence of evidence is never evidence of absence.** A scan that finds no
matches because there are no files to scan has not verified anything. Say which of
the two happened — a reader cannot tell from a green result.

---

## Phase 1: Parse Arguments

Determine whether this is a sprint retrospective (`sprint-N`) or a milestone retrospective (`milestone-name`).

---

## Phase 1b: Check for Existing Retrospective

Before loading any data, glob for an existing retrospective file:

- For sprint retrospectives: `production/retrospectives/retro-[sprint-slug]-*.md`
  (also check `production/sprints/sprint-[N]-retrospective.md` as an alternate location)
- For milestone retrospectives: `production/retrospectives/retro-[milestone-name]-*.md`

If a matching file is found, use `AskUserQuestion`:
- Prompt: "An existing retrospective was found: [filename]. How do you want to proceed?"
- Options:
  - `[A] Update existing — load it and add/revise sections with new data`
  - `[B] Start fresh — generate a new retrospective (archive the old one)`

If [A]: read the existing file and carry its content forward, revising sections with new data.
If [B]: continue to Phase 2 with a blank slate. Before writing the new file, rename the existing one with a `-archived-[date]` suffix. That rename is a write too: it happens in Phase 5, only once the ask there — which names it — is approved.

---

## Phase 2: Load Sprint or Milestone Data

Read the sprint or milestone plan from the appropriate location:

- Sprint plans: `production/sprints/`
- Milestone definitions: `production/milestones/`

**Also check for `production/sprint-status.yaml`**: if it exists, read it alongside the sprint plan. It is the authoritative source for actual story completion status (status: done, completed dates, blockers). Use it as the primary source for completion metrics in Phase 3. Fall back to markdown scanning only if the yaml does not exist. Note discrepancies between the yaml and the sprint plan (e.g., stories in yaml not in plan, or vice versa).

**If the file does not exist or is empty**, output:

> "No sprint data found for [sprint/milestone]. Run `/sprint-plan new` to create a
> sprint (`/sprint-status` only reads one), or provide the sprint details manually."

At `workflow: minimal` (resolved above) there are no sprints: offer to look back over the stories
closed so far instead (`production/epics/*/story-*.md` with `Status: Complete`).
At `qa.level: minimal` (resolved above) tests are waived, so a story closed
without one is not a finding; a Visual/Feel or UI story closed without its
retained screenshot still is.

Then use `AskUserQuestion` to present these options ([C] only at `workflow: minimal`):

- **[A] Provide data manually** — ask the user to paste or describe the sprint
  tasks, dates, and outcomes; use that as the source of truth for the retrospective.
- **[B] Stop** — abort the skill. Verdict: **BLOCKED** — no sprint data available.
- **[C] Look back over the closed stories** — use the stories with
  `Status: Complete` as the record of what was done.

If the user chooses [A], collect the data and continue to Phase 3 using what they provide.
If the user chooses [B], stop here.
If the user chooses [C], read those stories and continue to Phase 3. Sections that
need sprint data (planned vs actual, velocity, carryover, estimation accuracy)
are `NOT ASSESSED — NO DATA`.

Extract: planned tasks, estimated effort, owners, and goals.

Run git log for the sprint period to understand what was actually committed and when. Use the Bash tool (which uses Git Bash on Windows — the `2>/dev/null` is bash syntax, not PowerShell):

```
Bash: git log --oneline --since="4 weeks ago" 2>/dev/null || git log --oneline -20
```

Adjust the `--since` date to match the sprint duration if known from the sprint plan.

---

## Phase 3: Analyze Completion and Trends

Scan for completed and incomplete tasks by comparing the plan against actual deliverables. Check for:

- Tasks completed as planned
- Tasks completed but modified from the plan
- Tasks carried over (not completed)
- Tasks added mid-sprint (unplanned work)
- Tasks removed or descoped

Every story with `status: blocked` in `production/sprint-status.yaml` goes under
Blockers Encountered, with its `blocker` field as the Blocker, and gets an action
item in Action Items for Next Iteration.

Scan the codebase for TODO/FIXME trends:

- Count current TODO/FIXME/HACK comments
- Compare to previous sprint counts if available (check previous retrospectives)
- Note whether technical debt is growing or shrinking

Read previous retrospectives (if any) from `production/retrospectives/` to check:

- Were previous action items addressed?
- Are the same problems recurring?
- How has velocity trended?

With no earlier sprint or retrospective, Velocity Trend keeps only the current
sprint's row and reads `NOT ASSESSED — NO DATA`, and Previous Action Items
Follow-Up is that one line — no invented earlier rows, no empty table.

---

## Phase 4: Generate the Retrospective

```markdown
## Retrospective: [Sprint N / Milestone Name]
Period: [Start Date] -- [End Date]
Generated: [Date]

### Metrics

| Metric | Planned | Actual | Delta |
|--------|---------|--------|-------|
| Tasks | [X] | [Y] | [+/- Z] |
| Completion Rate | -- | [Z%] | -- |
| Story Points / Effort Days | [X] | [Y] | [+/- Z] |
| Bugs Found | -- | [N] | -- |
| Bugs Fixed | -- | [N] | -- |
| Unplanned Tasks Added | -- | [N] | -- |
| Commits | -- | [N] | -- |

### Velocity Trend

| Sprint | Planned | Completed | Rate |
|--------|---------|-----------|------|
| [N-2] | [X] | [Y] | [Z%] |
| [N-1] | [X] | [Y] | [Z%] |
| [N] (current) | [X] | [Y] | [Z%] |

**Trend**: [Increasing / Stable / Decreasing — or `NOT ASSESSED — NO DATA` with no earlier sprint to compare]
[One sentence explaining the trend]

### What Went Well
- [Observation backed by specific data or examples]
- [Another positive observation]
- [Recognize specific contributions or decisions that paid off]

### What Went Poorly
- [Specific issue with measurable impact -- e.g., "Feature X took 5 days
  instead of estimated 2, blocking tasks Y and Z"]
- [Another issue with impact]
- [Do not assign blame -- focus on systemic causes]

### Blockers Encountered

| Blocker | Duration | Resolution | Prevention |
|---------|----------|------------|------------|
| [What blocked progress] | [How long] | [How it was resolved] | [How to prevent recurrence] |

### Estimation Accuracy

| Task | Estimated | Actual | Variance | Likely Cause |
|------|-----------|--------|----------|--------------|
| [Most overestimated task] | [X] | [Y] | [+Z] | [Why] |
| [Most underestimated task] | [X] | [Y] | [-Z] | [Why] |

**Overall estimation accuracy**: [X%] of tasks within +/- 20% of estimate

[Analysis: Are we consistently over- or under-estimating? For which types of
tasks? What adjustment should we apply?]

### Carryover Analysis

| Task | Original Sprint | Times Carried | Reason | Action |
|------|----------------|---------------|--------|--------|
| [Task that was not completed] | [Sprint N-X] | [N] | [Why] | [Complete / Descope / Redesign] |

### Technical Debt Status
- Current TODO count: [N] (previous: [N])
- Current FIXME count: [N] (previous: [N])
- Current HACK count: [N] (previous: [N])
- Trend: [Growing / Stable / Shrinking]
- [Note any areas of concern]

### Previous Action Items Follow-Up

| Action Item (from Sprint N-1) | Status | Notes |
|-------------------------------|--------|-------|
| [Previous action] | [Done / In Progress / Not Started] | [Context] |

### Action Items for Next Iteration

| # | Action | Owner | Priority | Deadline |
|---|--------|-------|----------|----------|
| 1 | [Specific, measurable action] | [Who] | [High/Med/Low] | [When] |
| 2 | [Another action] | [Who] | [Priority] | [When] |

### Process Improvements
- [Specific change to how we work, with expected benefit]
- [Another improvement -- keep it to 2-3 actionable items, not a wish list]

### Summary
[2-3 sentence overall assessment: Was this a good sprint/milestone? What is
the single most important thing to change going forward?]
```

---

## Phase 5: Save Retrospective

Present the retrospective and top findings to the user (completion rate, velocity trend, top blocker, most important action item).

Ask: "May I write this to `production/retrospectives/retro-sprint-[N]-[date].md`?" (or `production/retrospectives/retro-[milestone-name]-[date].md` for milestone retrospectives)

After Start fresh in Phase 1b, the same ask also names the rename: "…and rename
`[old file]` to `[old file name]-archived-[date].md`?" On yes, rename first, then
write; on no, neither happens.

If yes, write the file, creating the `production/retrospectives/` directory if needed. Verdict: **COMPLETE** — retrospective saved.

If no, stop here. Verdict: **BLOCKED** — user declined write.

---

## Phase 6: Next Steps

At `workflow: minimal` (resolved above), which has no sprints, skip this question:
point to the retrospective file and say its action items go into the brief's build
order.

Otherwise, use `AskUserQuestion`:
- Prompt: "Retrospective complete. The action items and velocity data are ready. Would you like to start sprint planning now with this data pre-loaded?"
- Options:
  - `[A] Yes — open sprint planning with retro action items and velocity delta pre-populated`
  - `[B] No — I'll reference the retrospective file manually when I'm ready`

If the user selects [A]: Proceed to invoke `/sprint-plan new`, passing the retrospective file path and a summary of the action items and velocity change so the sprint planner can reference them.

- If this was a milestone retrospective, run `/gate-check` to formally assess readiness for the next phase.

### Guidelines

- Be honest and specific. Vague retrospectives ("communication could be better") produce vague improvements. Use data and examples.
- Focus on systemic issues, not individual blame.
- Limit action items to 3-5. More than that dilutes focus.
- Every action item must have an owner and a deadline.
- Check whether previous action items were completed. Recurring unaddressed items are a process smell.
- If this is a milestone retrospective, also evaluate whether the milestone goals were achieved and what that means for the overall project timeline.

© Donchitos · MIT · Donchitos/Claude-Code-Game-Studios

Similar skills

All skills for Notes, tasks and projects →

From the same set72

Project sponsors

Companies that keep this analytics open
Gold sponsor

Impressions, clicks and code copies — open statistics. We keep the numbers public for the same reason NeBlask itself is public. Become a sponsor